Made under the Electricity Act 1989

8 statutory instruments made using powers in the Electricity Act 1989, newest first. Each one is explained section by section in plain English.

The Plugs and Sockets etc. (Safety) Regulations 1994 and Electricity Safety, Quality and Continuity Regulations 2002 (Amendment) Regulations 2026

Published: Fri 17th Jul 26 Came into force: Thu 27th Aug 26

Authorized the use of standard plugs for plug-in solar microgenerators up to 800 watts and mandated compliance with a new interim product specification.


These Regulations permit the use of standard plugs for plug-in solar microgenerators with a maximum output of 800 watts, provided they meet specific safety criteria.

They authorize notified bodies to approve plugs that do not fully conform to British Standard BS 1363 solely because they facilitate electricity generation.

The instrument applies to manufacturers of plug-in solar devices, notified bodies responsible for safety certification, and consumers in England, Wales, Scotland, and Northern Ireland (though grid-related amendments apply only to Great Britain).

Read More

The Renewables Obligation (Amendment) Order 2026

Published: Fri 27th Mar 26 Came into force: Fri 27th Mar 26

Switched the inflation indexing for renewable electricity buy-out prices and mutualisation caps from RPI to CPI effective April 2026.


This Order amends the Renewables Obligation Order 2015 to change the inflation index used for adjusting the buy-out price and the mutualisation cap for electricity suppliers in England and Wales.

It replaces the Retail Prices Index (RPI) with the Consumer Prices Index (CPI) for all obligation periods starting on or after 1 April 2026.

These changes apply to all licensed electricity suppliers who must either produce Renewables Obligation Certificates (ROCs) or make cash buy-out payments to the Gas and Electricity Markets Authority (Ofgem).

Read More

The Electricity and Gas (Energy Company Obligation) (Amendment) (Specified Period) Order 2026

The instrument extended the specified period and critical procedural deadlines for the Energy Company Obligation (ECO) scheme by nine months, concluding the main obligation period on December 31st, 2026.


This Statutory Instrument, made on March 25th, 2026, amends the preceding Electricity and Gas (Energy Company Obligation) Order 2022 by extending the overall period of the Energy Company Obligation (ECO) scheme by nine months, shifting the end date for the home-heating cost reduction target from March 31st, 2026, to December 31st, 2026.

The Order also adjusts several associated deadlines for remaining procedural steps, applications, and measure approvals under the ECO scheme across England, Wales, and Scotland, ensuring consistency with the newly defined final date.

Read More

The Electricity (Individual Exemption from the Requirement for a Transmission Licence) (Dogger Bank A) (Amendment) Order 2025

Published: Wed 19th Nov 25 Came into force: Thu 18th Dec 25

* Extended the electricity transmission licence exemption for the Dogger Bank A Offshore Wind Farm for one year, from December 2025 to December 2026.


The Secretary of State made this Order under powers granted by the Electricity Act 1989 to amend the existing 2025 Order concerning the Dogger Bank A Offshore Wind Farm.

This amendment specifically extends the date until which the project is exempt from the requirement to hold an electricity transmission licence, changing the expiry date from December 19, 2025, to December 18, 2026, and the Order applies to England, Wales, and Scotland.

Read More

The Electricity (Individual Exemption from the Requirement for a Generation Licence) (Riverside Energy Park) (England) Order 2025

Published: Tue 9th Sept 25 Came into force: Wed 1st Oct 25

An exemption from the electricity generation license requirement was granted to Riverside Energy Park Limited for its Riverside 2 facility in Belvedere, London, subject to specific conditions.


The Electricity (Individual Exemption from the Requirement for a Generation Licence) (Riverside Energy Park) (England) Order 2025 grants an indefinite exemption to Riverside Energy Park Limited from the requirement of obtaining a generation license for its Riverside 2 energy from waste facility in Belvedere, London.

This exemption is subject to conditions limiting power export to 100 megawatts and requiring connection to the national grid.

The order applies only to England and was enacted under the Electricity Act 1989.

Read More

The Electricity Act 1989 (Requirement of Consent for Solar Generating Stations) (England) Order 2025

Published: Fri 27th Jun 25 Came into force: Wed 31st Dec 25

The order amended the Electricity Act 1989 to increase the permitted capacity for solar generating stations in England to 100 megawatts.


The Electricity Act 1989 (Requirement of Consent for Solar Generating Stations) (England) Order 2025, effective December 31, 2025, amends the 1989 Act to increase the permitted capacity of solar generating stations in England from 50 to 100 megawatts before requiring Secretary of State consent.

The Order applies to England and Wales and is supported by a separate impact assessment.

Read More

The Electricity (Individual Exemption from the Requirement for a Supply Licence) (JG Pears Power Limited) (England) Order 2025

Published: Wed 4th Jun 25 Came into force: Wed 25th Jun 25

A temporary exemption from the electricity supply license requirement was granted to JG Pears Power Limited to supply electricity to High Marnham Green Energy Business Park in England.


This order temporarily exempts JG Pears Power Limited from needing an electricity supply license to provide power to the High Marnham Green Energy Business Park in England.

The exemption, granted under the Electricity Act 1989, runs until December 31, 2034, and is subject to conditions limiting the maximum electricity supply to 37 megawatts.

The order's justification involves facilitating the prompt delivery of renewable energy while acknowledging a lack of significant impact on the public or private sectors.

Read More

The Electricity (Individual Exemption from the Requirement for a Transmission Licence) (Spiorad na Mara) (Scotland) Order 2025

Published: Wed 26th Mar 25 Came into force: Wed 7th May 25

The Order exempted Spiorad na Mara Limited from the requirement for an electricity transmission licence for its offshore generating station in Scotland.


The Electricity (Individual Exemption from the Requirement for a Transmission Licence) (Spiorad na Mara) (Scotland) Order 2025 grants an indefinite exemption from the requirement for Spiorad na Mara Limited to hold an electricity transmission licence for the transmission of electricity from its offshore generating station in the Isle of Lewis to an onshore substation.

The Secretary of State made the order under powers granted by the Electricity Act 1989, after consultation with Scottish Ministers, based on the unique circumstances of the offshore project.

The exemption applies to Scotland only, takes effect on May 7, 2025 and does not require a full impact assessment due to the anticipated lack of significant impact on the public or private sectors.

Read More